This email is to inform you that on the nights of November 7th, 8th, 14th & 15th, 2014 we will be closing ALL LANES on the QEW Toronto Bound (NORTHBOUND) at the Burlington Bay Skyway Bridge. (Weather permitting)

CLOSURE TIME:
Friday November 7th, 2014 22:00 to Saturday November 8th, 06:00(Cancelled)
Saturday November 8th, 2014 23:00 to Sunday November 9th, 08:00(Cancelled)

Friday November 14th, 2014 22:00 to Saturday November 15th, 06:00
Saturday November 15th, 2014 23:00 to Sunday November 16th, 08:00

We will be closing the QEW for the purposes of removing the Work Platforms and Environmental Enclosures prior to the winter months on the Burlington Skyway Bridge as part of our contract with the MTO (MTO Contract 2013-2047).

During the full closure, traffic will be routed off of the Toronto Bound QEW at Eastport Drive and detoured along Eastport Drive to rejoin the QEW. Traffic measures for this detour will be deployed as per contract drawings and specifications including traffic detour signage and OPP traffic assistance at traffic light intersection at Lakeshore and Eastport Drive.

This notification is being conveyed to you as per Operational Constraints contained in MTO Contract 2013-2047.

Should you have any questions or concerns please contact the undersigned.

Kevin Cooper
Project Manager
Dayson Industrial Services Inc.
416-427-8002
 