"We are told that in those pioneering times, the principal topics of discussion were Politics and Religion. Running a close third in the post-war years was Public Works, which entailed the planning and building of canals."
"The year 1823 was one of major interest to the people of Hamilton and district, for on 19 March, an Act was passed authorizing construction of the Burlington Canal. The canal commissioners were John Aikman,Wm. Chisholm and Wm. Applegarth John Chisholm was appointed Collector of Customs."
'As the gangs of men began digging through the sand of Burlington Beach in 1825, those interested in shipping were preparing for the canal's completion by building wharves.'
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=S2
1827 - ""Proposal for completing the works at the Burlington Bay Canal will be received by the Subscriber until Friday, the 24th August (proximo) agreeable to the annexed schedule - and in conformity with the several Acts of the Legislature of this Province made in reference thereto. Plans and Specifications may be seen by intending contractors on application to me.
By order of the Commissioners,
W. J. Kerr, Secretary.
Burlington Beach, July 27, 1827.
Work to be done to complete the Burlington Bay Canal,
11 Cribs of timber, to complete return pier head in L. Ontario, south side including all materials such as piles, planking, workmanship, stone and everything else necessary.
7 Cribs, ditto, south side, Burlington Bay. Additional crib work to improve south pier in L. Ontario.
37 Oak Piles, for return pier head, 30 feet long and 15 inches diameter, 2,610 cu. ft.
88 Oak Piles, for south pier in L. Ontario, 8,640 cu. ft.
75 Oak Piles, ditto.
18 Oak Piles, to put beneath the south abutment of the bridge.
10 Oak Piles, to repair breaches in south pier.
10 Oak Piles, for south pier head in Burlington B.
12 Oak Piles, for south pier head in L. Ontario.
114 Oak Piles, for abutment of bridge north side; to repair breaches in north pier, in the Lake and the Bay, and to repair head of breakwater.
Pointing, driving and shoeing with iron such of said piles as may be necessary.
97 Bollards, or mooring posts, of oak; pointing and driving same.
35,000 feet of 3 inch pine plank for covering the piles.
7,000 cu. ft. pine timber, squared, for building the old work up to the required height.
700 feet of hand rail on outer side of south pier, L. Ontario.
40 cords of heavy stone for backing up the return pier head.
20 cords, ditto, for pier head.
Excavating channel to 12 feet depth, throughout - 3,000 cu. yds.
One swivel bridge, complete.
One Lighthouse on return pier head, with Argand oil lamp, complete.
One Capstan, on pierhead."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1827
1828 - "On 30 June 1828, an item appeared in the Niagara Gleaner regarding arbitration in connection with the Burlington Canal. The arbitrators were stated to be Daniel O'Reilly, for the Commissioners, Edward McBride for the contractor, and Allan Napier MacNab. They had evidently awarded £12,938 to the contractor, Strowbridge, but the Commissioners not only refused to pay this money, but demanded that the Attorney General show cause as to why they should. One wonders if MacNab, who was not known for his saintliness, and his two Irish friends had a little boodle in mind, including, of course Mr. Strowbridge."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1828
1829 - "The still-unfinished Burlington Canal had sufficient depth of water and the passage of schooners inbound with general cargo and outward bound with wheat and flour was frequent."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1829
1830 - "In April, 1830, a short-lived newspaper called the Gore Balance ublished a few items of interest. On the 8 April, it informed its readers that the dredge was still working in the Burlington Canal and that it was
expected that the work would be completed "in a few days"
Four days later, this paper published a quite impressive list of sailing vessels, passing through the canal: GENERAL BROCK, Capt. Kerr, REBECCA and ELIZA, Capt. Zealand, BRITANNIA, Capt. Roberts, MARGARET, Capt. Mitchell, TRAFALGAR, Capt. Enoe, TELEGRAPH, Capt. Boylan, MINERVA, Capt. Kent,BROTHERS, Capt. Chas. McIntosh, MOHAWK CHIEF, Capt. Campbell,PEACOCK,Capt. Philo D. Bates, and KINGSTON PACKET,Capt. Knox."
""Canal Fever" was indeed rampant in the land and unfortunately, was not always guided by wisdom. The contractor on the Burlington Canal was building timber cribs and filling them with beach gravel, in the hope that they would hold the sides of the channel. The Lake had no trouble at all undermining
them and playfully shifting them out of line."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1830
1834 - "In this season of 1834, the Burlington Canal was said to be completed, at least until the next major rehabilitation had to be carried out."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1834
1842 - "In Hamilton, on the 6 October, W. M. Shaw, Canal Engineer, was calling for tenders for the reconstruction of the Burlington Canal."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1842
1843 - "The St. Catharines Journal, on the 10 August 1843, noted that the activities at the Burlington Canal had started. It stated:
"The railroad from the Mountain to the Beach is now completed and the hauling of the stone has commenced. A great quantity of timber has been delivered and every arrangement made to proceed in the work with vigour. The new canal is to be made on the site of the old one. The South Pier will form the breastwork for the protection of the new work which is to be laid down. The North Wall is to be removed and the Canal widened to about 160 feet."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1843
Fred told me that the cars for this railroad were hauld by horses from the beach to the escarpment. And At the escarpment, both the stone and the horses were loaded into the cars and the cars then rolled back down to the beach under the force of gravity.
1848 - "Citizens of the district, feeling the need of a swing bridge over the Burlington Canal, had submitted a petition to the Dept. of Public Works in Montreal. The request was refused on the grounds that "abutments" would have to be built and these would impede navigation and the flow of the current through the canals causing the deposit of sediments. There must have been a political reason for this, and the Hamilton Spectator pointed its inky finger at "that eminent engineer, Mr. Killaly."
It would have been obvious to many of its readers, that the negative decision was not the result of any engineering study and the letter containing the refusal could have been written equally well by the village
idiot."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1848
"The year 1823 was one of major interest to the people of Hamilton and district, for on 19 March, an Act was passed authorizing construction of the Burlington Canal. The canal commissioners were John Aikman,Wm. Chisholm and Wm. Applegarth John Chisholm was appointed Collector of Customs."
'As the gangs of men began digging through the sand of Burlington Beach in 1825, those interested in shipping were preparing for the canal's completion by building wharves.'
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=S2
1827 - ""Proposal for completing the works at the Burlington Bay Canal will be received by the Subscriber until Friday, the 24th August (proximo) agreeable to the annexed schedule - and in conformity with the several Acts of the Legislature of this Province made in reference thereto. Plans and Specifications may be seen by intending contractors on application to me.
By order of the Commissioners,
W. J. Kerr, Secretary.
Burlington Beach, July 27, 1827.
Work to be done to complete the Burlington Bay Canal,
11 Cribs of timber, to complete return pier head in L. Ontario, south side including all materials such as piles, planking, workmanship, stone and everything else necessary.
7 Cribs, ditto, south side, Burlington Bay. Additional crib work to improve south pier in L. Ontario.
37 Oak Piles, for return pier head, 30 feet long and 15 inches diameter, 2,610 cu. ft.
88 Oak Piles, for south pier in L. Ontario, 8,640 cu. ft.
75 Oak Piles, ditto.
18 Oak Piles, to put beneath the south abutment of the bridge.
10 Oak Piles, to repair breaches in south pier.
10 Oak Piles, for south pier head in Burlington B.
12 Oak Piles, for south pier head in L. Ontario.
114 Oak Piles, for abutment of bridge north side; to repair breaches in north pier, in the Lake and the Bay, and to repair head of breakwater.
Pointing, driving and shoeing with iron such of said piles as may be necessary.
97 Bollards, or mooring posts, of oak; pointing and driving same.
35,000 feet of 3 inch pine plank for covering the piles.
7,000 cu. ft. pine timber, squared, for building the old work up to the required height.
700 feet of hand rail on outer side of south pier, L. Ontario.
40 cords of heavy stone for backing up the return pier head.
20 cords, ditto, for pier head.
Excavating channel to 12 feet depth, throughout - 3,000 cu. yds.
One swivel bridge, complete.
One Lighthouse on return pier head, with Argand oil lamp, complete.
One Capstan, on pierhead."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1827
1828 - "On 30 June 1828, an item appeared in the Niagara Gleaner regarding arbitration in connection with the Burlington Canal. The arbitrators were stated to be Daniel O'Reilly, for the Commissioners, Edward McBride for the contractor, and Allan Napier MacNab. They had evidently awarded £12,938 to the contractor, Strowbridge, but the Commissioners not only refused to pay this money, but demanded that the Attorney General show cause as to why they should. One wonders if MacNab, who was not known for his saintliness, and his two Irish friends had a little boodle in mind, including, of course Mr. Strowbridge."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1828
1829 - "The still-unfinished Burlington Canal had sufficient depth of water and the passage of schooners inbound with general cargo and outward bound with wheat and flour was frequent."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1829
1830 - "In April, 1830, a short-lived newspaper called the Gore Balance ublished a few items of interest. On the 8 April, it informed its readers that the dredge was still working in the Burlington Canal and that it was
expected that the work would be completed "in a few days"
Four days later, this paper published a quite impressive list of sailing vessels, passing through the canal: GENERAL BROCK, Capt. Kerr, REBECCA and ELIZA, Capt. Zealand, BRITANNIA, Capt. Roberts, MARGARET, Capt. Mitchell, TRAFALGAR, Capt. Enoe, TELEGRAPH, Capt. Boylan, MINERVA, Capt. Kent,BROTHERS, Capt. Chas. McIntosh, MOHAWK CHIEF, Capt. Campbell,PEACOCK,Capt. Philo D. Bates, and KINGSTON PACKET,Capt. Knox."
""Canal Fever" was indeed rampant in the land and unfortunately, was not always guided by wisdom. The contractor on the Burlington Canal was building timber cribs and filling them with beach gravel, in the hope that they would hold the sides of the channel. The Lake had no trouble at all undermining
them and playfully shifting them out of line."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1830
1834 - "In this season of 1834, the Burlington Canal was said to be completed, at least until the next major rehabilitation had to be carried out."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1834
1842 - "In Hamilton, on the 6 October, W. M. Shaw, Canal Engineer, was calling for tenders for the reconstruction of the Burlington Canal."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1842
1843 - "The St. Catharines Journal, on the 10 August 1843, noted that the activities at the Burlington Canal had started. It stated:
"The railroad from the Mountain to the Beach is now completed and the hauling of the stone has commenced. A great quantity of timber has been delivered and every arrangement made to proceed in the work with vigour. The new canal is to be made on the site of the old one. The South Pier will form the breastwork for the protection of the new work which is to be laid down. The North Wall is to be removed and the Canal widened to about 160 feet."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1843
Fred told me that the cars for this railroad were hauld by horses from the beach to the escarpment. And At the escarpment, both the stone and the horses were loaded into the cars and the cars then rolled back down to the beach under the force of gravity.
1848 - "Citizens of the district, feeling the need of a swing bridge over the Burlington Canal, had submitted a petition to the Dept. of Public Works in Montreal. The request was refused on the grounds that "abutments" would have to be built and these would impede navigation and the flow of the current through the canals causing the deposit of sediments. There must have been a political reason for this, and the Hamilton Spectator pointed its inky finger at "that eminent engineer, Mr. Killaly."
It would have been obvious to many of its readers, that the negative decision was not the result of any engineering study and the letter containing the refusal could have been written equally well by the village
idiot."
http://www.maritimehistoryofthegreatlakes.ca/documents/Brookes/default.asp?I
D=Y1848
Last edited: